Project information:

Project location: Ashdod, Israel

Project size: 26x50x4m steel structure warehouse

Project details: Hot rolled H section type steel structure frame+0.5mm white metal roof+Skylight panel.

Project process: Production has been finished and in transit now

Project background:

The client sent request to Dorian in Jan, 2023. After deep communication with client, Dorian learned that this was his own project and would be used as a cow shed.

The original size what client initially planned is 20x60x5m. The client required that the building has good insulation performance, so according to the customer's requirements, rock wool sandwich panels with good insulation effect were selected as the roof and wall panels. Dorian engineer finished proposal and quotation within 12 hours of getting the details of project, and after one day of study and discussion with his architect, the client asked Dorian team to check shipping cost for reference.

Meanwhile, due to local policy requirements, the client had to apply for construction approval from the local authority in advance. As a result, the client informed Dorian that he was now in the process of applying for construction approvals from the local government and would not purchase a steel building until he had received the permits, which would take approximately several months to obtain.

Project design:

Dorian team has also kept in touch with client. After three months, client got permission and contacted Dorian team he would decide to go ahead the order. Moreover, the final project size was changed and need to be redesigned. Besides, client also informed Dorian team he would put solar panels on the roof later.  

The final project size was 50m*26m*4m, which was required to equip with rock wool sandwich roof pane and the wall would be open. The most importantly, the roof load of solar panels also be taken into account, usually the roof load is about 25kg/m2 if added solar panels on it. If you have also this requirement, pls inform us in advance so that our engineer can take this factor into account during designing. 

1300 Square Meter Steel Structure Building In Israel 11300 Square Meter Steel Structure Building In Israel 7

Dorian engineer finished complete proposal and quotation in eight hours. It needs 2x40HQ containers to load the goods after calculation by the engineer. After checked the shipping cost, it exceed client budget. Therefore , On the basis of client’s demand, Dorian suggest adopting metal sheeting roof for the project, which not only can decrease materials cost but also can reduce one container and save shipping cost.

The client accept this suggestion and Dorian update quotation based on this proposal.

The updated quotation was provided to client within half of an hour. Dorian’s efficiency and service were deeply appreciated by client and he ordered to Dorian after one days.

Project production and delivery:

Dorian workers finished production within 17days after confirming the details and load all the goods in the one 40ft container.

1300 Square Meter Steel Structure Building In Israel 21300 Square Meter Steel Structure Building In Israel 8

All the goods are in transit now and we will share you with more information if any update later.

1300 Square Meter Steel Structure Building In Israel 31300 Square Meter Steel Structure Building In Israel 41300 Square Meter Steel Structure Building In Israel 51300 Square Meter Steel Structure Building In Israel 6

Pls don’t hesitate to contact us if you have requirement about steel structure, welcome to your inquiry freely!

Published

June 21, 2025

Share